SAP Material Requirement Planning (MRP) MM01

Material requirements planning (MRP) is to monitor stocks and in particular to automatically generate order proposals for purchasing or production. For this purpose you can define re-ordering levels to your stocks/material, by this SAP automatic intimate the defined user when the stock level go down from the re-ordering level.
Field Name R/O/C Description
MRP Type R Key that determines whether and how the material is planned.
Select as follows:
 - VB for stores and spares
 - PD for production related materials
 - ND for material with no planning requirement
Reorder Point C Applicable if VB is selected.
The system compares available warehouse stock with the reorder level. If available stock falls below the reorder level, an order proposal is generated.
Example: 10

Field NameR/O/CDescription
MRP ControllerRThe MRP controller or group of MRP controllers responsible for material planning for the material.
Lot SizeRIs used to calculate the purchase order quantities.
LTC specific lot sizes are:
for VB - EX (lot for lot order qty), HB (replenish to max.)
for PD - PW weekly lot sizing key is to be selected.
for PD - MB monthly lot sizing key is to be selected.